1 . If 60 men can complete a work in 30 days working 12 hrs a day. In how many days will 90 men complete the work, working 8 hr a day?
[ A ]    20 days
[ B ]    27 days
[ C ]    30 days right
[ D ]    31 days
Answer : Option C
Explanation :
60 men working 12hr a days complete a work in 30 days
1 Man work in 1 hr a day complete a work in = 30 × 60 × 12 = 21600 days
∴ 90 men working 8hr a day can complete the same work in = $21600\over90x8$ = 30 days