1 . A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men that should be appointed so that the whole work will be finished in time ?
[ A ]    75 [ B ]    100 right
[ C ]    125 [ D ]    50
Answer : Option B
Explanation :