1 . P and Q can complete a piece of work in 14 days and 16 days respectively. P begins to do the work and they work alternately one at a time for one day each. The whole work will be completed in–
A.14$7\over15$ days
B.7$7\over15$ days
C.14$7\over8$ days
D.7$7\over8$ days
[ A ]    a
[ B ]   
[ C ]    c right
[ D ]    d
Answer : Option C
Explanation :
Workspace Report error