1 . A, B and C can complete a work separately in 24, 36 and 48 days respectively. They started together but C left after 2 days of start and A left 3 days before the completion of work. In how many days will the work be completed ?
[ A ]    20 days
[ B ]    18 days
[ C ]    16 days
[ D ]    12 days right
Answer : Option D
Explanation :